Midweek: Focusing on Lift Installation

Construction on our Hunter North expansion began just a short 5 months ago and now with all 5 new trails and 4 glades cut, graded, and snowmaking installation well underway, our Lift Operations teams turn their sights to our new high speed six passenger chairlift.

Parts including X-arms, sheaves, catwalks, lift towers and more have arrived in our staging area near the new entrance to Hunter North and crews have started assembling these parts in anticipation for our lift tower installation.

Hunter North Project Management have scheduled for our lift towers to be installed next week on Monday, October 15th (weathering pending of course). This process will involve a specialized heavy duty helicopter flying our towers from the staging area by the entrance to their installation site where crews will receive the part and install it on its foundation.

If you plan to be in the area to witness it, it will surely be a sight to see but if not you can be sure that we will be taking plenty of pictures and will have a full recap video to show you on the day of the installation!